Project Timeline

Construction Updates will be provided as they become available.
The newly enhanced YMCA facilities are estimated to be open Spring 2025.

2024

April 15-28, 2024

These few weeks were all about water. The water main to the existing building was replaced and storm piping was laid underground to carry away rain water to our newly dug retention pond.

April 1, 2024

Construction begins! Construction crews mobilize and initial sitework begins, including relocating the playground equipment for safekeeping.

2023

March 27-29

Geotechnical surveys are conducted to investigate subsurface conditions and materials, determine the physical and chemical properties of the earth materials, evaluate slopes and design foundations! A total of 19 sites were surveyed.

2022

September 2022
June 2022
June 2022
April 2022
January 2022

Completed schematic and design development
Hired CG Schmidt
Requested construction proposals
Completed Master Planning
Hired Zimmerman Architectural Studios

2021

December 2021

October 2021
September 2021
September 2021

June 2021

Awarded Workforce Innovation Grant in the amount of $3,779,479 to address the lack of childcare and youth development infrastructure
Established community partners for a Youth Development Center
Began touring 10+ other YMCAs
Conducted market research (SWWRPC, GCDC, focus groups & community surveys)
Click here to read a summary of our market research
Capital Campaign Prep Committee was created

 

2019

September 2019

YMCA Board of Directors engages in strategic planning

 

2018

June 2018

CG Schmidt conducted a facility assessment